The structural scheme of coal mining machine to achieve coal wall crushing

Coal Wall Spalling Mechanism and Grouting Reinforcement
To control the problem of coal wall spalling in large mining height working faces subject to mining, considering the Duanwang Mine fully mechanized working face, the mechanism of coal wall spalling in working faces was investigated by theoretical analysis, numerical simulation 2024年10月18日 Compared with traditional coal wall spalling prevention and control methods, the advanced grooving and pressure relief technology proposed in this paper for preventing Coal‐wall spalling prevention mechanism using advance‐grooving 2023年1月3日 PDF One of the primary factors affecting safe and effective mining in fully mechanized mining faces with large mining heights is coal wall sloughing Find, read and (PDF) Research on the Mechanism and Control Technology of Coal With the increase of mining height, the problem of coal wall spalling in the working face gradually worsens Hydraulic support and its face guard structure are the key pieces of equipmentSchematic of the coal wall supported by the hydraulic support

Research on the Mechanism and Control Technology of Coal Wall
In order to simulate the characteristics of the coal wall in the large mining height working face at various mining heights, the FLAC3D numerical method was used2023年1月3日 This paper establishes the mechanical model of the coal wall and uses the deflection theory for the mechanics of materials to find the maximum point of the deflection of Research on the Mechanism and Control Technology of Coal Wall 2024年10月18日 This study analyzes 2201 working faces with large mining heights in the Haiwan No 3 Mine by investigating the mechanical response law of coal walls under the Coal‐wall spalling prevention mechanism using advance‐grooving 2024年4月24日 To study the coal falling trajectory of cutting coal and rock using a spiral drum, optimal cutting parameters were obtained, efficient cutting using a spiral drum was achieved, Coal falling trajectory and strength analysis of drum of shearer

A new method for improving coal wall stability in longwall mining
2023年4月12日 The main methods to control coal wall stability are as follows: (a) increasing the strength of the coal wall by injecting chemical materials such as superfine cement and 2021年2月1日 To improve the coal recovery rate and reduce excavation of the mining roadway, the 111 mining method of longwall mining was proposed in the former Soviet Union based on Innovation and future of mining rock mechanics ScienceDirect2024年10月18日 Compared with traditional coal wall spalling prevention and control methods, the advanced grooving and pressure relief technology proposed in this paper for preventing coal wall spalling in large mining height working faces of shallow buried coal seams actively modifies the roof structure and coal body stress mechanism through groovingCoal‐wall spalling prevention mechanism using advance‐grooving Currently coal companies, especially in South Kalimantan, have not yet been or only slightly entered the postmining stage, although part of the mining blocks have been totally exploited, so that Collaborative automation of coal mining machines in

Design and performance of a triaxial load cell for conical picks
2024年10月1日 Fig 1 (a) shows a shearer drum from a longarm coal mining machine, primarily used for coal cutting and loading; Fig 1 (b) shows a cutting drum from a roadheader, mainly used for rock fragmentation in tunnel construction; Fig 1 (c) illustrates a milling drum from a road planer, used for breaking up waste road surfaces; and Fig 1 (d) depicts a pick head from a mining machine drums for three coal seam conditions: coal, rock and mixed coal rock, and analyzed the in˝u ence of taper angle, intercept distance, spiral angle, pick arrangement and traction Guochao Zhao1, Xin Jin1 , Lijuan Zhao1, Wenchao Zhou2 Nature2022年10月18日 2 intelligent process of coal mines1Realize the intelligent of fully mechanized mining and build a less manned and unmanned underground mining environment, which can improve the efficient cutting Research on Key Technology of Coal and Rock Cutting State Download scientific diagram Schematic of the coal wall supported by the hydraulic support from publication: Analysis of the Protection Performance of Face Guard for Large Mining Height Schematic of the coal wall supported by the hydraulic support

A conceptual scheme improvement approach based on the
2019年2月1日 Request PDF A conceptual scheme improvement approach based on the performance value of the principle solution taking a coal mining machine as a case study Improving existing schemes based on 2024年9月17日 The secondary mining movement in nonpillar coal extraction causes significant overrun damage to flexible formwork concrete walls, leading to extensive deformation of roadway roof and bottom platesPredictive model for the instability of flexible formwork concrete wall 2022年5月27日 The combined mining scheme and foundation strengthening scheme can ensure the safe operation of highvoltage pylons and provide a new method for the stability control of ground buildings in coal Study on the Combined Mining Scheme for Coal Resources data, then calculate the average thickness of the coal wall accurately to improve the preperception ability of the coal mining machine on the surface of the coal wall before mining Next, a regression model was constructed for the relationship between drum speed, traction speed, average coal wall thickness, and cutting energy consumption Shearer parameter optimization and low energy consumption mining

Optimal layout of blasting holes in structural anisotropic coal seam
1 Introduction Coal mine methane (CMM) occurs naturally in coal seams as the adsorbed and free state, which is a kind of green energy with high burning value and little emissions after burning []However, CMM is one of the threats for underground coal mine because the accumulated methane in the entry has the potential to trigger methane explosive, and high 2019年2月1日 The PS of the coal mining machine is extracted from the CDSIS SYSTEM to obtain a schematic of the initial PS for the coal mining machine Next, based on the PS improvement process illustrated in Fig 8, the corresponding WSK is obtained A suitable operation method is determined to relate the WSK and generate a new PSA conceptual scheme improvement approach based on the Unsupervised Intelligent Method for Cutting Pick State RecognitionAn Unsupervised Intelligent Method for Cutting Pick State 2023年4月12日 To propose a support stiffness based method for improving the stability of coal wall, static stiffness of the support and fracture development of the coal wall are monitored during retraction period of a panel in the second coal mine of Zhaogu coalfield It is revealed that the range of support stiffness falls between 50 and 450 MN/m In face length direction, support A new method for improving coal wall stability in longwall mining

Analysis and construction of the coal and rock cutting state
2023年3月1日 The recognition of cutting state of coalrock is the key technology to realize “unmanned” mining in coal face In order to realized realtime perception and accurate judgment of coalrock 2023年3月1日 The recognition of cutting state of coalrock is the key technology to realize “unmanned” mining in coal face In order to realized realtime perception and accurate judgment of coalrock cutting state information, this paper combined the field test sampling, construction technology of complex coal seam, virtual prototype technology, bidirectional coupling Analysis and construction of the coal and rock cutting state 2021年1月23日 It is difficult to accurately calculate the lump coal rate in a fully mechanized mining face Therefore, a numerical simulation of the coal wall cutting process, which revealed the crack expansion Numerical simulation of coal wall cutting and lump coal 753 Screening and Crushing Coal Machinery 7531 Crushing Coal Machinery Take the HSZ800 type ring hammer coal crusher as an example, the main structural features as shown in Fig 752 Using the ring shaft 5 working with toothed hammer rings 4 active installations on the tumbler 6 In the second half ofOperation and Maintenance of Coal Conveying System Screening

Numerical Simulation of Coal Wall Cutting and Lump Coal
2020年8月4日 It is difficult to accurately calculate the lump coal rate in a fully mechanized mining face Therefore, a numerical simulation of the coal wall cutting process, which revealed the crack expansion Longwall mining extracts all machineminable coal between the floor and ceiling within a contiguous block of coal, known as a panel, leaving no support pillars within the panel area Panel dimensions vary over time and with mining conditions but currently average about 900 feet wide (coal face width) and more than 8,000 feet long (the minable extent of the panel, measured in Coal Mining and Processing Methods The National Academies Therefore, when constructing the numerical model of coal cowlassisted drum cutting and loading, it is necessary to establish the top and bottom plate wall, drum and coal cowl models, as well as structural models of rocker arms and scraper shovels, etc Due to the small thickness of the thin seam mining, the diameter of the drums is approximately the same as the thickness of the seamInfluence of coal cowl parameters on the coal loading process of 2024年9月5日 Accurately obtaining the geological characteristic digital model of a coal seam and surrounding rock in front of a fully mechanized mining face is one of the key technologies for automatic and continuous coal mining operation to realize an intelligent unmanned working face The research on how to establish accurate and reliable coal seam digital models is a hot topic The Construction and Application of a Digital Coal Seam for

Numerical Simulation of Coal Wall Cutting and Lump Coal
2 / 19 increasing the lump coal rate in a mine With this goal in mind, current research has mainly focused on the structural modification of coal winning machines and the optimization of coal 2019年12月1日 A mathematical hydraulic support selftracking model for threemachine cooperative mining is proposed to address low efficiency and difficulties in strategy evaluation of a fully mechanized coal faceAn operation optimization method of a fully mechanized coal mining 2023年1月1日 The realization of intelligent mining is the only method for realizing highquality development in the coal industry As the forefront working link in mine production, achieving automatic roadway (PDF) Applications of Machine Vision in Coal Mine Fully 2023年6月12日 Coal mining can have significant environmental consequences The extraction, processing, and transportation of coal can contribute to various forms of pollution and land degradation It is essential to mitigate these impacts to ensure sustainable mining practices The key environmental concerns associated with coal mining in South Africa include:South African Coal Mining Techniques Methods, Impact Future

Structural design of coal mine galleries ResearchGate
Download scientific diagram Structural design of coal mine galleries from publication: Characteristic Study of Visible Light Communication and Influence of Coal Dust Particles in Underground 2023年8月10日 Coal mining is moving in the direction of green and intelligent mining, which is of great importance to improve the coal mining rate, protect the environment and achieve the sustainable development of coal mines Coal mining causes strata movement, resulting in surface subsidence and consequent damage to farmland and construction facilitiesEnergies Special Issue : Green and Intelligent Mining of Coal2024年2月9日 31 3D modeling of the shearing section In this study, the MG2×55/250BWD type shearer was used The drum pick arrangement is shown in Fig 2A, along with the pick designationsThe drum diameter is 800 mm, while the drum hub diameter is 465 mm Teeth inclination angles from Sections A to D were 15°, 12°, 8°, and 3°, respectively, while the Numerical study of forces acting on the drum cutting coal with 2021年8月10日 Stress is one of the main factors influencing coal and gas outbursts The apparent effects of the crustal stress, the structural stress, and the mininginduced stress increase as the depth of The Relationship between MiningInduced Stress and Coal Gas

Coal‐wall spalling prevention mechanism using advance‐grooving
2024年10月18日 Compared with traditional coal wall spalling prevention and control methods, the advanced grooving and pressure relief technology proposed in this paper for preventing coal wall spalling in large mining height working faces of shallow buried coal seams actively modifies the roof structure and coal body stress mechanism through groovingCurrently coal companies, especially in South Kalimantan, have not yet been or only slightly entered the postmining stage, although part of the mining blocks have been totally exploited, so that Collaborative automation of coal mining machines in 2024年10月1日 Fig 1 (a) shows a shearer drum from a longarm coal mining machine, primarily used for coal cutting and loading; Fig 1 (b) shows a cutting drum from a roadheader, mainly used for rock fragmentation in tunnel construction; Fig 1 (c) illustrates a milling drum from a road planer, used for breaking up waste road surfaces; and Fig 1 (d) depicts a pick head from a Design and performance of a triaxial load cell for conical picksmining machine drums for three coal seam conditions: coal, rock and mixed coal rock, and analyzed the in˝u ence of taper angle, intercept distance, spiral angle, pick arrangement and traction Guochao Zhao1, Xin Jin1 , Lijuan Zhao1, Wenchao Zhou2 Nature

Research on Key Technology of Coal and Rock Cutting State
2022年10月18日 2 intelligent process of coal mines1Realize the intelligent of fully mechanized mining and build a less manned and unmanned underground mining environment, which can improve the efficient cutting Download scientific diagram Schematic of the coal wall supported by the hydraulic support from publication: Analysis of the Protection Performance of Face Guard for Large Mining Height Schematic of the coal wall supported by the hydraulic support2019年2月1日 Request PDF A conceptual scheme improvement approach based on the performance value of the principle solution taking a coal mining machine as a case study Improving existing schemes based on A conceptual scheme improvement approach based on the 2024年9月17日 The secondary mining movement in nonpillar coal extraction causes significant overrun damage to flexible formwork concrete walls, leading to extensive deformation of roadway roof and bottom platesPredictive model for the instability of flexible formwork concrete wall

Study on the Combined Mining Scheme for Coal Resources
2022年5月27日 The combined mining scheme and foundation strengthening scheme can ensure the safe operation of highvoltage pylons and provide a new method for the stability control of ground buildings in coal data, then calculate the average thickness of the coal wall accurately to improve the preperception ability of the coal mining machine on the surface of the coal wall before mining Next, a regression model was constructed for the relationship between drum speed, traction speed, average coal wall thickness, and cutting energy consumption Shearer parameter optimization and low energy consumption mining